Project Milestones
Project milestones for the Johnson Ferry/Abernathy Road Widening Projects include the following:
Phase I : Public Involvement
-
March – April 2002: Develop Public Involvement Plan
-
May 2002: CAC Meetings
-
December 2002: Public Information Meeting
-
February and March 2003: CAC Meetings
-
March 2003: Public Information Meeting
-
June 2003: CAC Meeting
Phase II: Concept Development
Phase III: Traffic Studies
-
April 2002: Travel Demand Modeling and Projections
-
April – October 2002: Traffic Model Analysis
-
March – April 2003: Prepare Traffic Studies Report
Phase IV: Environmental Studies and Analyses
-
April 2002 – March 2003: Preliminary Studies and Analyses; Coordination with Resource Agencies
-
July 2003 – December 2004: Complete Environmental Studies and Prepare Draft Environmental Assessment
-
March 2005: Draft Environmental Document Public Hearing
Phase V: Preliminary Plans
Phase VI: Right of Way Approval and Acquisition
-
May 2005 – July 2005: Completion of right-of-way plans
-
July 2005: Approval of the right-of-way plans
-
August 2005: Begin the acquisition of right-of-way
Phase VII: Final Plans