GDOT Header Image

Johnson Ferry & Abernathy Road

With the increasing population growth in Cobb County over the last few decades, Johnson Ferry Road and Abernathy Road in Fulton County have become major transportation corridors for vehicles traveling from Cobb County into Fulton County, especially to gain access to SR 400 and I-285. Recognizing that this corridor lacked sufficient capacity, in 1987 the Georgia Department of Transportation (GDOT) developed concepts for improving Johnson Ferry Road and Abernathy Road.

 

Project Information

 

Project Details

Project Contractor:    C.W.Matthews
Project Status:  Project is currently under construction
Scheduled Completion Date:  January 2013

 

Status Update

April 2013
  • This project is 99% complete.
  • There are ongoing punch list items.
  • Time has stopped for the contractor as of February 28, 2013.

 View News and Activities Archive

 

 

Disclaimer: The Georgia Department of Transportation carefully maintains the information offered on this website, but makes no expressed or implied warranty of any kind and assumes no responsibility for errors or omissions. No responsibility is assumed for incidental or consequential damages in connection with or arising from the use of the information or programs contained herein.