SR 30 FROM LAKE BLACKSHEAR TO SR 300 CONN W OF CORDELE - TIA
Project ID: 422470- Notice to Proceed Date:
Project Manager: Joe Gillis Construction Percent Complete: 99.98%
Office: TIA Current Completion Date:
County: Crisp Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 013 Construction Contractor: REEVES CONSTRUCTION COMPANY
State House District: 148 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed construction will begin east of the Lake Blackshear bridge and end east of the US 280/SR 30 and SR 300 Connector/Old Albany Road intersection. The project will consist of widening the existing two-lane US 280/SR 30 roadway to two 12-foot travel lanes in each direction, with a 4-foot flush median. The existing pavement will be resurfaced and new lanes and shoulders will be added where necessary. Rural shoulders along US 280/SR 30 are proposed to be 10-foot wide with 4-foot paved shoulders. The shoulders will have roadside ditches. At Gum Creek, the existing 200¿ x 47¿-3¿ US 280/SR 30 bridge is proposed to be widened by 28¿-3¿ to accommodate the eastbound travel lanes. A new at-grade crossing for the Heart of Georgia Railroad is proposed at the existing location.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2000$574,885.67 
PE (Preliminary Engineering)2009$899,901.25 
ROW (Right of Way)2014$1,917,187.75 
CST (Construction)2014$22,801,970.25 
PE (Preliminary Engineering)2015$3,180,415.00 
CST (Construction)2021$5,000,000.00 