SR 316 @MCCARTY RD &SAM SIMS EXT FM SAM SIMS RD TO POWELL RD
Project ID: 0013909 Notice to Proceed Date:
Project Manager: Albert V. Shelby III Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Barrow Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 047 Construction Contractor:
State House District: 119 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Long Range Program More Information...
Right of Way Authorization: Contact Us
Project Description:
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2030$975,750.002/25/2020
CST (Construction)2034$11,893,350.00 
Project Search (TransPI) Map
 Project Documents
 