CR 65/WINDSOR SPRINGS FM WILLIS FORMAN RD TO TOBACCO RD-TIA
Project ID: 250610- Notice to Proceed Date:
Project Manager: Krystal Stovall Dixon Construction Percent Complete: 88.72%
Office: Program Delivery Current Completion Date:
County: Richmond Work Completion Date:
Congressional District: 012 Construction Contract Amount:
State Senate District.: 022 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 125, 126 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
Project STP00-7007-00(006) begins south of the intersection of CR 65/Windsor Spring Road/Temp. SR 1128 and Willis Foreman Road and terminates at the intersection of CR 65/Windsor Spring Road/Temp. SR 1128 and Tobacco Road. This project is approximately 3.3 miles long. The existing two-lane, 6-foot graded shoulder Urban Minor Arterial facility will be widened to four 11-foot wide lanes (two lanes in each direction) separated by a raised median. 16-foot shoulders with curb and gutter and an 8-foot wide multi-use trail will also be constructed on both sides of the roadway.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2000$79,826.52 
ROW (Right of Way)2010$7,272,815.008/9/2010
ROW (Right of Way)2011$2,697,815.008/9/2010
PE (Preliminary Engineering)2014$25,000.00 
CST (Construction)2014$32,289,995.1210/15/2013