SR 24 FM E OF CHAMBERS BROOKS SPRING RD TO W OF HELTON LN
Project ID: 0015878 Notice to Proceed Date:
Project Manager: Jonathan Andrew Clark Construction Percent Complete: 57.31%
Office: Program Delivery Current Completion Date:
County: Washington Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 026 Construction Contractor: PITTMAN CONSTRUCTION COMPANY
State House District: 128 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project SR 24 corridor improvements will follow the existing alignment, 3-lane alignment as the centerline of the new widening and will be 4 lanes divided by a 4-foot flushed median. The project begins east of Chambers Brooks Spring Road to west of Helton Lane.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2018$767,500.00 
ROW (Right of Way)2020$1,025,000.007/8/2019
CST (Construction)2022$12,256,920.388/14/2020
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports