 TIMELINE FOR ACQUISITIONS

Setting a Schedule

Timeline Starts at ROW Authorization and Ends at Let Date

(If true Relocations are equal to or exceed 5% of project total parcel count, add 3 months for Relocations)
~Consequential Displaceesare excluded~

0-8
Parcels
0-30
Parcels
31-75
Parcels
76-200
Parcels
201-Plus
Parcels
9 Months
12 Months 18 Months 24 Months 30 Months
15 Months
(If two or more relocations)
21 Months
(Relocationcount ≥5%)
27 Months
(Relocationcount ≥5% )
33 Months
(Relocationcount ≥5%)
  • Simple
  • Rural/Bridge Project
  • No improvements
  • No Consequential Damages
  • No Govt. OwnedParcels

       

SPECIAL NOTE: Plan revisions submitted after authorization have the potential to negatively impact schedule up to six additional months.