Percentage of Projects Constructed on Schedule​​​

Description

Each contract executed to build a project includes an agreed upon time frame by GDOT and the Contractor to complete construction. However, sometimes necessary extensions occur. This measure tracks how well GDOT is constructing projects within the agreed upon contract time.

Strategic Objective

Complete the construction of 80% or more of all projects within the agreed upon contract time.

Road to Improvement

GDOT fell short of its FY 2016 target, completing only 57% of projects on time. GDOT will continue to explore ways to improve coordination with existing utilities; communication with our contractors, and the quality of plans to meet the target in this area.

Data source: GDOT

Disclaimer: The Georgia Department of Transportation makes no representation or warranties, implied or expressed, concerning the accuracy, completeness, reliability, or suitability for any particular purpose of this information and data contained on this website.