SR 92 Relocation & Widening (Douglasville)

SR 92 Douglasville​​​​​​

Interim Completion Map

View Map​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

The SR 92 relocation and widening project in the City of Douglasville is separated into three phases:

Phase I: 0006900

Project is the first of three phases to relocate SR 92 through the City of Douglasville. It includes grade separation of relocated SR 92 at SR 5/US 78 Bankhead Hwy, at NSC RR and at Strickland Street. The project includes the closing of at-grade RR crossing at Brown Street, Mozley Street, and SR 92/Dallas HWY, while relocating the McCarley Street at-grade RR crossing 100' to the west of the existing crossing for a better grade.

Phase II: 0006901

Project is second of three phases to relocate SR 92 in the City of Douglasville. The project begins at Pine Drive (south of I-20 Interchange at SR 92) and goes north on new location to SR 5/US 78/Bankhead Highway where it will tie to phase one (PI# 0006900).

Phase III: 720970-

Project is the third of three phases to relocate SR 92 through the City of Douglasville. The project begins at the intersection of relocated SR 92 and relocated Ellis Street where it connects with Phase 1. It ends just north of the existing intersection of SR 92/Dallas Highway and Malone Road.

 Status: May 2019

Highlights 4

Schedule

SR 92 Underpass Open to Traffic: May 2021
Overall Completion Date: August 2021
On schedule to have the light poles and high mast installed around I-20 & SR 92/Duralee Ln by approximately end of August-early September (weather permitting)
On schedule to have the Railroad Bridge (bridge #2) done before the Norfolk target date (approximately Jan 5th )

Highlights 1

Status
Project Construction is 66% Completed as of August 2019

Majority of the base for the structures have been poured and is awaiting the required strength before installing the remaining structures

Highlights 2

Utilities

Contractor, C. W. Matthews (CWM), water sub-contractor is scheduled to begin making the necessary adjustments to all drainage systems. This will allow C.W. Matthews to begin the required roadway work for the north section of the project from Ellis St to Dallas Hwy (Old 92). This work is estimated to be completed by early 2020.

 Anticipated Completion Date

August 2021 

       Photo Gallery

        Public Meeting DocumentsDate
        Questions and Responses October 2018
        PresentationJune 2018
        Questions and Responses June 2018
        PresentationMay 2018

         ‭(Hidden)‬ Upcoming Public Meetings

         Contacts

        Oluchukwu Anyaebosi, Project Manager
        Georgia Department of Transportation
        600 West Peachtree St., NW
        Atlanta, GA 30308
        (404) 631-1540
        E-mail


        Lankston O. Johnson, Construction Manager
        Georgia Department of Transportation
        600 West Peachtree St., NW
        Atlanta, GA 30308
        (404) 559-6699