I-285 & SR 400 Improvements

The proposed improvements are designed to aid in reducing traffic congestion and improve safety in the area surrounding the I-285/SR 400 interchange in metro Atlanta. New flyover ramps, new collector-distributor lanes and other facilities to aid east-west travel on along I-285 and north-south travel along SR 400 would be constructed. 

The proposed improvements are achieved in two projects:

  • I-285/SR 400 Interchange Reconstruction P.I. # 0000784
  • SR 400 Collector-Distributor (CD) Lanes P.I. # 721850-

 

 

 

Project Information

In order to achieve maximum efficiency, economic benefit and cost-effectiveness for the region, the Department now proposes to construct the two stand-alone projects as one Design-Build-Finance (DBF), Public-Private Partnership (P3). The combined design-build cost is estimated at $1.056 billion.

Fact Sheet   Location   Schedule  


Apparent Best Value Development Partner: North Perimeter Contractors

  • Lead Contractor: Ferrovial Agroman US Corp
  • Lead Designer: The Louis Berger Group and Neel-Schaffer, Inc.
  • View Press Release

 ‭(Hidden)‬ Project Information -Old

In order to achieve maximum efficiency, economic benefit and cost-effectiveness for the region, the Department now proposes to construct the two stand-alone projects as one Design-Build-Finance (DBF), Public-Private Partnership (P3). The combined design-build cost is estimated at $1.056 billion.
Fact Sheet

Location

The proposed improvements will be provided along I-285 from west of Roswell Road in Fulton County to east of Ashford-Dunwoody Road in DeKalb County (4.3 miles), and along SR 400 from Glenridge Connector to Spalding Drive (6.2 miles), for a total project length of 10.5 miles.

Schedule

Right of Way Acquisition

  • GDOT is currently acquiring required property for project P.I. # 721850- and will complete acquisition by June 30, 2016.
  • GDOT is currently acquiring required property for project P.I. # 0000784 (between Glenridge Drive and the MARTA overpass) and will complete acquisition by December 31, 2016.
  • The selected Developer will acquire required property, west of Glenridge Drive and east of the MARTA overpass, for project P.I. # 0000784.

Procurement Phase

Financial Close with the Developer is anticipated to occur in April 2016.

Final Design/Construction Phase

  • The Developer is anticipated to receive Notice to Proceed with Final Design in April 2016.
  • Construction is anticipated to begin in late 2016/early 2017.
  • Construction is anticipated to be complete by Spring 2020.

 

 