Home -> Projects -> Project Info -> Special Projects -> SR 92 Relocation & Widening

SR 92 Relocation & Widening (Douglasville)

SR 92 Douglasville​​​​​​

Time-Lapse

View time-lapse videos and photos of the SR 92 project.

View Time-Lapse​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

The SR 92 relocation and widening project in the City of Douglasville is separated into three phases:

Phase Project ID Description
Phase I 0006900 Project is the first of three phases to relocate SR 92 through the City of Douglasville. It includes grade separation of relocated SR 92 at SR 5/US 78 Bankhead Hwy, at NSC RR and at Strickland Street. The project includes the closing of at-grade RR crossing at Brown Street, Mozley Street, and SR 92/Dallas HWY, while relocating the McCarley Street at-grade RR crossing 100' to the west of the existing crossing for a better grade.
Phase II 0006901 Project is second of three phases to relocate SR 92 in the City of Douglasville. The project begins at Pine Drive (south of I-20 Interchange at SR 92) and goes north on new location to SR 5/US 78/Bankhead Highway where it will tie to phase one (PI# 0006900).
Phase III 720970- Project is the third of three phases to relocate SR 92 through the City of Douglasville. The project begins at the intersection of relocated SR 92 and relocated Ellis Street where it connects with Phase 1. It ends just north of the existing intersection of SR 92/Dallas Highway and Malone Road.

 Status: May 2019

Highlights 4

Schedule

SR 92 Underpass Open to Traffic: May 2021
Overall Completion Date: August 2021

Highlights 1

Status
Project Construction is 64% Completed

Installing sound wall barriers north of Cooper Street
Sewer main rerouted on Davis Drive
Installed Gravity Wall
Roadway widening continues
Targeted blasting after pre-event inspections
Excavated and hauled more than 30,000 cubic yards of material to prepare for underpass

Highlights 2

Utilities

16-inch water main rerouted on E. Strickland Road
Continued relocation of sewer and water lines

 Anticipated Completion Date

November 2020


       Photo Gallery

        Public Meeting DocumentsDate
        Questions and Responses October 2018
        PresentationJune 2018
        Questions and Responses June 2018
        PresentationMay 2018

         ‭(Hidden)‬ Upcoming Public Meetings

         Contacts

        Oluchukwu Anyaebosi, Project Manager
        Georgia Department of Transportation
        600 West Peachtree St., NW
        Atlanta, GA 30308
        (404) 631-1540
        E-mail


        Lankston O. Johnson, Construction Manager
        Georgia Department of Transportation
        600 West Peachtree St., NW
        Atlanta, GA 30308
        (404) 559-6699
        E-mail