The Georgia DOT is replacing the CR 5813/College Street bridge over Norfolk Southern Railroad and partially replacing the SR 247/ Pio Nono Ave bridge over Norfolk Southern Railroad in Bibb County. These projects are vital for the freight-rail transportation network to allow for double stacked rail cars.


Macon Bridges

Anticipated Schedule

SR 247/Pio Nono Ave Bridge


Q1
2020

Construction activities begin


Q2
2020

30-day road closure


CR 5813/College Street Bridge


Q4
2019

AT&T relocation began


Q1
2020

Construction activities begin


Q2
2020

College Street five-month closure begins

Anticipated Schedule

SR 247/Pio Nono Ave Bridge

Q1
2020

Construction activities begin

Q2
2020

30-day road closure

CR 5813/College Street Bridge

Q4
2019

AT&T relocation began

Q1
2020

Construction activities begin

Q2
2020

College Street five-month closure begins


Quick Facts

Bridges

College Street bridge and SR 247/ Pio Nono Ave bridge over Norfolk Southern Railroad are two separate bridge locations in Bibb County.

Project Costs

The projects will cost $18.6 million and are scheduled to be completed in Q4 2020.

Design-Build

Design-Build Team: Wright Brothers/Neel-Schaffer



 Contacts

For additional information, please contact the following:

Rick O’Hara, Project Manager
Innovative Delivery